Electrical Safety for AV and Events

Plan power, use temporary distribution and RCDs correctly, check equipment and work safely

7 min readUpdated

Contents

Before you start

Every AV system runs on mains power, and events often run on temporary power set up in a few hours, in a hurry, in places it was never designed for. Electrical faults can cause shocks, fires and equipment damage, and a tripped circuit in the middle of an event is a very public failure. This guide explains the rules, how to plan power for AV, how temporary distribution works, the role of RCDs and earthing, equipment testing, and the everyday habits that keep everyone safe.

This guide is not a substitute for competence. Electrical installation, temporary distribution, generator connection and testing must be carried out by people who are competent to do so. The aim here is to help AV people plan, ask the right questions, spot problems and work safely with the power they are given.

The rules

  • The Electricity at Work Regulations 1989 require electrical systems and equipment used at work to be safe, maintained and worked on only by competent people. They apply to employers, the self-employed and employees.
  • BS 7671 (the IET Wiring Regulations) covers electrical installations, including permanent wiring in venues and installed AV systems.
  • BS 7909 is the code of practice for temporary electrical systems for entertainment and related purposes: events, concerts, exhibitions, film and TV. It covers planning, design, installation, inspection and documentation of temporary power.
  • The IET Code of Practice for In-service Inspection and Testing of Electrical Equipment covers checking portable equipment (often called PAT testing).
  • Venues and event organisers often have their own rules, such as requiring test certificates for all equipment, or that only the venue's electrician connects to the house supply.

Plan the power

  1. List every piece of equipment with its power: amplifiers, powered speakers, LED screens, projectors, lighting, computers, catering. Use the maximum power for sizing, and the typical power for estimating running costs and generator fuel.
  2. Group the loads by area and type: sound, video, lighting. Keep sound on separate circuits from lighting dimmers and motors where possible, to reduce noise and interference.
  3. Work out the current: on a single-phase 230 V supply, current = power ÷ 230. 3,000 W is about 13 A. On three-phase, divide the load across the phases.
  4. Allow headroom. Do not plan to load circuits beyond about 80% of their rating continuously, and allow for start-up surges.
  5. Find out what the venue provides: the number and rating of outlets and three-phase supplies, where they are, and who connects to them.
  6. Draw a power plan showing supplies, distribution, circuits and loads, and share it with the venue and the event electrician.

The Single & Three-Phase Power Calculator, LED Power & Heat Calculator and Cable Size Calculator (BS 7671) help with the numbers.

Power quality

  • Start-up surges: amplifiers, LED screens and power supplies draw a large current for a moment at switch-on. Switching everything on at once can trip breakers. Use sequencers or switch on in stages.
  • Earth leakage: electronic equipment leaks a small current to earth through its filters. Many items on one RCD can add up and cause nuisance tripping.
  • Harmonics: modern electronic loads draw current in pulses, which on three-phase supplies can add up in the neutral. Distribution and generators should be designed with this in mind.

Temporary distribution

Temporary power distribution from a supply to distribution boxes, circuits and equipment SupplyMain distroSound distroVideo distroLighting distro venue or generatorthree-phase, RCDs16 A circuits16 A circuits16 A circuitsamps, deskLED, projectorsfixtures
A typical temporary system: the supply feeds a main distribution unit, which feeds smaller distribution boxes for each department, each with protected circuits.

Connectors

ConnectorUse
Blue 16 A and 32 A (BS EN 60309, single-phase 230 V)The standard for temporary power at events, outdoors and on stage. Robust, weather-resistant and keyed so different voltages cannot be mixed.
Red 16 A to 125 A (BS EN 60309, three-phase 400 V)Feeds to distribution units and large equipment.
13 A plugs (BS 1363)Fine indoors for small equipment, but not robust or weatherproof enough for demanding temporary use.
Locking IEC and Powercon-type connectorsMains into equipment, and for linking power between devices where the manufacturer allows.

Good practice

  • Use proper distribution boxes with circuit breakers and RCDs, not chains of extension leads and adaptors.
  • Never overload sockets, leads or reels. Check the rating of every lead, adaptor and connector in the path.
  • Fully unwind cable reels under load: a coiled reel can overheat and melt.
  • Do not daisy-chain extension leads or multi-way adaptors.
  • Respect power link limits on equipment that passes mains through (power out to the next device): the total current must stay within the connector and cable rating.
  • Use cables suited to the environment: rubber-sheathed flexible cable (such as H07RN-F) outdoors and on stage, sized for the current and length.
  • Protect cables from damage and people from trips: route them away from walkways, use cable ramps across routes, and keep connections off the ground and out of water outdoors.
  • Label distribution, circuits and long cables.

RCDs and earthing

Earthing

The earth connection carries fault current safely away and makes protective devices operate if something goes wrong. Every Class I (earthed) item must have a sound earth connection, all the way back to the supply.

Never remove, disconnect or "lift" the mains earth to cure hum or buzz. Doing so can make metal cases live in a fault, with fatal results. Cure hum with balanced connections, DI boxes, audio isolation transformers or ground lift switches on audio connections, which lift the audio screen, not the mains earth.

RCDs

  • An RCD (residual current device) switches off the supply very quickly if current leaks to earth, such as through a person touching a live part. A 30 mA RCD gives important additional protection against electric shock.
  • Temporary systems for events should have 30 mA RCD protection on final circuits supplying socket outlets and equipment people can touch, as BS 7909 and BS 7671 require.
  • Test RCDs with their test button before each event, and have them tested with an RCD tester as part of the system's inspection.
  • Avoid nuisance tripping by spreading electronic loads over enough RCD-protected circuits. RCBOs (a combined breaker and RCD for each circuit) mean one fault only takes out one circuit.
  • The MCB & RCD Selection Guide explains breaker types and RCD choices.

Generators

Generators need an earthing arrangement designed for the situation, often including an earth electrode, and correct connection of the neutral and earth. They must be sized for the load, including surges and harmonics, and positioned safely for fuel, exhaust and noise. Generator connection is a job for a competent event electrician.

Equipment inspection and testing

  • User checks before every use: look at plugs, leads and cases for damage, burn marks, loose parts, damaged cable sheaths or exposed conductors, and wrong fuses. Remove anything damaged from use immediately and label it.
  • Formal inspection and testing by a competent person at intervals suited to the equipment and how it is used. Hired and touring equipment takes more abuse than equipment in a cupboard, so is checked more often. Keep the records and labels up to date.
  • Fuses: 13 A plugs should carry the right fuse for the equipment (often 3 A, 5 A or 13 A, as the manufacturer specifies). Never replace a fuse with a higher rating, or with anything other than a fuse.
  • Visiting equipment: performers' and presenters' equipment should be checked too. Many venues insist on a current test label.
  • Keep liquids away from equipment and distribution, and keep equipment ventilated.

Safe working habits

  1. Know where the power comes from and where to switch it off, including the emergency stop for the event.
  2. Isolate before working on anything that opens up mains parts, such as LED cabinets, amplifier internals or distribution, and make sure it cannot be switched back on. Only competent people should work inside mains equipment.
  3. Switch off before connecting large loads, and power up in the agreed order.
  4. Keep connections dry: outdoors, use weatherproof connectors, keep joints off the ground and covered.
  5. Do not improvise: no cut-and-taped cables, no bare-wire connections, no home-made adaptors.
  6. Watch for warning signs: warm plugs or cables, burning smells, buzzing, flickering or repeated tripping. Switch off and investigate.
  7. Report and record faults and near misses.

In an emergency

  • If someone receives an electric shock and is still in contact, switch off the power or separate them from the source using something non-conductive, without touching them directly.
  • Call 999, and give first aid if trained.
  • For electrical fires, switch off the power if it is safe to do so and use a suitable extinguisher (CO₂ or dry powder). Never use water on electrical equipment.

Installed AV systems

  • Permanent wiring for AV equipment (dedicated circuits for racks, LED screens and projectors) must be installed, tested and certified to BS 7671 by a qualified electrician.
  • Plan rack power with enough circuits, sequencing and, for critical systems, a UPS. Keep mains and audio cabling apart in racks and containment.
  • Leave space and ventilation for heat; amplifiers and LED power supplies produce a lot of it.
  • Ask for the electrical installation certificate and keep it with the AV documentation, along with the periodic inspection schedule.

Event power checklist

  • Power plan drawn up with loads, supplies, circuits and distribution
  • Venue rules and connection arrangements agreed
  • Competent event electrician arranged for temporary distribution and generators
  • Distribution with breakers and 30 mA RCD protection, RCDs tested
  • Equipment checked and in date for inspection and testing
  • Cables sized, protected, routed away from walkways and fully unwound
  • Outdoor connections weatherproof and off the ground
  • Power-up order agreed and emergency isolation known
  • System inspected and documented before use, as BS 7909 requires